| 0 | | 50% | NORTHPARK OVERPASS PROJECT (T-1013) | 403 days | Thu 8/8/19 | Wed3/10/21 |
| 1 | √ | 100% | Contract Excecution | 0 days | Thu 8/8/19 | Thu 8/8/19 |
| 2 | | 66% | Project Management | 395 days | Thu 8/8/19 | Fri 2/26/21 |
| 3 | | 34% | - Project Management | 395 days | Thu 8/8/19 | Fri 2/26/21 |
| 4 | | 97% | - Subconsultant Contracting | 115 days | Tue 9/3/19 | Fri 3/27/20 |
| 10 | | 29% | Survey | 94 days | Wed 11/13/19 | Fri 3/27/20 |
| 11 | √ | 100% | - Site Visit to Confirm Survey Needs | 0 days | Wed 11/13/19 | Wed 11/13/19 |
| 12 | | 29% | - Design Survey | 42 days | Thu 1/30/20 | Fri 3/27/20 |
| 13 | √ | 100% | -- Submit Horiz. & Vert. Controls to McKim & Creed | 2 days | Thu 1/30/20 | Fri 1/31/20 |
| 14 | | 50% | -- RR Elevation Survey | 20 days | Mon 2/3/20 | Fri 2/28/20 |
| 15 | | 0% | -- Topographic Updates | 20 days | Mon 3/2/20 | Fri 3/27/20 |
| 16 | | 0% | -- Design Survey Submitted to HNTB | 0 days | Fri 3/27/20 | Fri 3/27/20 |
| 17 | | 34% | UPRR Crossing/Encroachment Agreements | 395 days | Thu 8/8/19 | Fri 2/26/21 |
| 18 | | 34% | - Coordination Meetings | 395 days | Thu 8/8/19 | Fri 2/26/21 |
| 19 | | 34% | - Agreement Modifications and Submitals | 395 days | Thu 8/8/19 | Fri 2/26/21 |